The new flashcard feature is useful to memorize questions.
?Change your study mode
At any time, you can change the study mode, and alternate between the practice mode and the exam mode. In practice mode, you can configure for example the number of questions or tests, and other parameters to help you study.
Randomized | 10 Questions per Test | 20 Minutes | 70% to pass|
To re-configure your study mode again and change - for example - the number of tests, whether you have random questions and all other configuration parameters.
?Simulator Configuration
Auto-scroll: You can use the automatic scrolling of the questionnaire that occurs as soon as you answer one or all of the answers to a question correctly. Auto scrolling is activated if you answer a single answer, or as soon as you answer all the mandatory answers. Learning Mode: During learning mode you can get a real time result for your answer.
Free Test
Question: / 10
20:00Min. left
?Restart the current test
To restart the current test by clearing all your answers and the time used up to now. Warning: all answers will be lost.
Question: / 10
5.0(1071 Votes)
Quiz
Question 1/101/10
Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?
Select the answer:Select the answer
1 correct answer
A.
Non-excusable delay
B.
Compensable delay
C.
Non-compensable delay
D.
Excusable delay
The correct answer is A. Non-excusable delay. A delay is generally categorized based on who caused it and whether the contractor is entitled to extra time, money, or both. 1. Non-excusable delay This is a delay caused by the contractor or within the contractor’s control, such as poor planning, inadequate staffing, equipment breakdown due to negligence, or subcontractor problems. Result: - No time extension - No additional compensation - The contractor may even be liable for damages, such as liquidated damages This is why Option A is correct. 2. Compensable delay This is a delay caused by the owner or by someone the owner is responsible for, such as late drawings, site access problems, or owner-directed changes. Result: - Time extension - Additional compensation 3. Non-compensable delay This is a delay that may justify extra time but not extra money, usually due to events beyond the control of both parties, such as unusually severe weather or certain force majeure events. Result: - Time extension - No additional compensation 4. Excusable delay This is a delay that is beyond the contractor’s control and not the contractor’s fault. Result: - Usually a time extension - It may be compensable or non-compensable depending on the cause Summary: Only a non-excusable delay does not result in either a time extension or additional compensation for the contractor.
Right Answer: A
Quiz
Question 2/102/10
Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high- clearance bridge located very near an airport? The contractor has been awarded the contract.
Select the answer:Select the answer
1 correct answer
A.
The project plans and specifications
B.
The project geotechnical report
C.
The regulations published by the government aviation agency
D.
The government's report on future high-clearance bridge projects
The correct answer is D. The government's report on future high-clearance bridge projects A planner/scheduler preparing a baseline critical path schedule for a contractor’s awarded bridge project needs documents that directly affect how the current project must be built, sequenced, and constrained. Why the other choices are valuable: A. The project plans and specifications These are the most important documents for scheduling. They define the scope of work, required materials, construction methods, milestones, quality requirements, and contractual obligations. A schedule must be based on them. B. The project geotechnical report This can be very important because soil and subsurface conditions affect foundations, excavations, piling, dewatering, and construction sequencing. For a large bridge, geotechnical information can significantly influence the schedule logic and activity durations. C. The regulations published by the government aviation agency Since the bridge is very near an airport, aviation-related regulations are highly relevant. They may impose restrictions on crane heights, work hours, lighting, equipment, safety procedures, or approvals needed to avoid interference with air traffic. These can directly affect the baseline schedule. Why D is least valuable: D. The government’s report on future high-clearance bridge projects This document may be interesting for industry planning or future forecasting, but it does not directly govern the contractor’s current awarded project. It would not normally affect the current baseline schedule unless it contained some unusual requirement, which is unlikely. Because the scheduler is planning the present project, future-project reports have little or no direct value. Conclusion: The least useful document for planning the contractor’s baseline critical path schedule is D, because it is not directly related to the current bridge project’s scope, constraints, or execution requirements.
Right Answer: D
Quiz
Question 3/103/10
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):
Select the answer:Select the answer
1 correct answer
A.
The delay must affect the critical path.
B.
The delay must be concurrent with the delay attributable to both parties.
C.
The delay must not cause monetary harm to the defendant.
D.
The delay must affect the contractor's planned construction schedule.
The correct answer is A. The delay must affect the critical path. In construction and contract claims, a claimant is typically entitled to an extension of time only if the delay event actually impacts the project completion date. That usually means the delay must affect the critical path, which is the sequence of activities that determines the earliest possible completion of the project. Why A is correct: - If a delay affects only non-critical activities, the overall project finish date may not be delayed. - An extension of time is generally granted only when the delay affects the critical path and therefore pushes completion later. - For a delay to also be compensable, it usually must be a qualifying delay for which the claimant is entitled under the contract and law, but the key threshold for time relief is critical path impact. Why the other options are incorrect: B. The delay must be concurrent with the delay attributable to both parties. - Concurrency can affect whether time and/or money are recoverable, but it is not a requirement for entitlement to an extension of time. - In fact, concurrent delay often complicates or limits recovery rather than establishing it. C. The delay must not cause monetary harm to the defendant. - Whether the defendant suffers monetary harm is not the test for entitlement to an extension of time. - The issue is whether the claimant was delayed in completing the work because of a qualifying event. D. The delay must affect the contractor's planned construction schedule. - A planned schedule alone is not enough. - The delay must affect the actual critical path or completion date, not merely interfere with the contractor’s preferred sequence or baseline plan. Summary: To obtain an extension of contract time, the claimant must show that the delay event affected the critical path and delayed completion. That is why A is the best answer.
Right Answer: A
Quiz
Question 4/104/10
Which of the following is NOT required when initially planning a project?
Select the answer:Select the answer
1 correct answer
A.
Resource Identification and leveling.
B.
The duration of each task.
C.
A schedule that identifies tasks required on a project.
D.
Logical relationships between the tasks.
The correct answer is A. Resource Identification and leveling. When initially planning a project, the main focus is on defining the work that must be done and how the tasks relate to one another. This usually includes: - Identifying the tasks required for the project - Estimating the duration of each task - Determining the logical relationships or dependencies between tasks These elements are needed to build the project schedule and understand the sequence of work. Resource identification and leveling are important in project management, but they are not usually required at the very beginning of planning. Resource leveling is typically done later, after the schedule is created, to adjust workloads and resolve over-allocation of people or equipment. Why the other options are required: - B. The duration of each task: needed to estimate how long the project will take - C. A schedule that identifies tasks required on a project: essential for project planning - D. Logical relationships between the tasks: needed to determine task order and dependencies So, A is the best answer because resource identification and leveling are not initially required in the planning stage.
Right Answer: A
Quiz
Question 5/105/10
Which of the following is NOT a tool or technique used to perform scope planning?
Select the answer:Select the answer
1 correct answer
A.
Benefit cost analysis.
B.
Schedule performance indexing.
C.
Expert Judgment.
D.
Alternatives identification.
The correct answer is B. Schedule performance indexing. Scope planning is the process of deciding how the project scope will be defined, documented, verified, and controlled. To do this, project managers use tools and techniques such as: - Benefit cost analysis: used to evaluate whether the project scope is worth pursuing based on expected benefits versus costs. - Expert judgment: used to gain insights from experienced people who can help define and plan project scope. - Alternatives identification: used to compare different ways of achieving the project objectives and determine the best scope approach. Schedule performance indexing, however, is not a scope planning tool or technique. It is a project schedule control metric used to measure schedule efficiency by comparing the value of work performed to the planned value. It belongs to schedule and performance management, not scope planning. Therefore, the option that is NOT used for scope planning is: B. Schedule performance indexing.
Right Answer: B
Quiz
Question 6/106/10
Which of the following are NOT considerations or constraints of the planning process for construction scheduling?
Select the answer:Select the answer
1 correct answer
A.
Consideration of all stakeholders.
B.
Value engineering.
C.
Project variables.
D.
Interest rate of owner's construction bonds.
The correct answer is D. Interest rate of owner's construction bonds. Construction scheduling and planning focus on factors that directly affect how a project is organized, coordinated, and executed. These typically include: A. Consideration of all stakeholders This is a real planning consideration. Scheduling must account for the needs and roles of owners, contractors, subcontractors, designers, regulators, and sometimes the public or end users. B. Value engineering This is also part of the planning process. Value engineering is used to improve project efficiency, reduce unnecessary cost, and maintain function and quality, all of which can influence scheduling decisions. C. Project variables These are definitely relevant. Project variables such as scope, site conditions, labor availability, weather, materials, and equipment all affect the schedule. D. Interest rate of owner's construction bonds This is not normally a direct consideration or constraint in construction scheduling. Bond interest rates are a financial issue, but they are not part of the core planning process for scheduling construction activities. Why D is correct: Construction scheduling is concerned with time, resources, dependencies, and project conditions. Financing details like bond interest rates may affect overall project economics, but they do not usually determine the construction schedule itself. Therefore, the option that is NOT a consideration or constraint of the planning process for construction scheduling is D.
Right Answer: D
Quiz
Question 7/107/10
What method offers the best chance of the schedule being used effectively to implement the project in the field?
Select the answer:Select the answer
1 correct answer
A.
Issue detailed schedule updates as frequently as possible.
B.
Obtain consent and agreement to the schedule from the key project personnel.
C.
Include detailed and stringent set of scheduling specifications in the contract.
D.
Allow large time contingencies on milestones and completion deadlines.
The correct answer is B. Obtain consent and agreement to the schedule from the key project personnel. A project schedule is only useful in the field if the people who must execute it understand it, accept it, and are willing to follow it. Getting agreement from key project personnel increases the likelihood that the schedule will be realistic, practical, and actually used as a management tool rather than just sitting on paper. Why B is best: - It creates buy-in from the people responsible for carrying out the work. - It improves cooperation and accountability. - It helps identify conflicts, missing activities, or unrealistic durations before the work starts. - It makes the schedule more likely to reflect how the project will actually be performed in the field. Why the other options are not as good: - A. Issue detailed schedule updates as frequently as possible. Frequent updates can help track progress, but they do not ensure the schedule is accepted or followed by the field team. Too many updates can even cause confusion if they are not well managed. - C. Include detailed and stringent set of scheduling specifications in the contract. Contract requirements can force scheduling processes, but they do not guarantee effective use in the field. Overly rigid specifications may create paperwork without improving day-to-day execution. - D. Allow large time contingencies on milestones and completion deadlines. Large contingencies may reduce risk of missing dates, but they do not improve coordination or commitment. Excessive float can also lead to weak planning discipline. In short, the best way to make a schedule effective in the field is to get the key project personnel to agree to it and commit to using it.
Right Answer: B
Quiz
Question 8/108/10
At a minimum, periodic reporting must be done at what interval?
Select the answer:Select the answer
1 correct answer
A.
Monthly.
B.
As requested by the project manager.
C.
As requested by the owner.
D.
As specified in the contract documents.
The correct answer is D. As specified in the contract documents. Periodic reporting means reports that are required on a recurring basis during the project, such as progress reports, status updates, cost reports, or schedule reports. The minimum frequency for these reports is not something that is set arbitrarily by the project manager or the owner on a case-by-case basis. Instead, it should be defined in the contract documents. Why D is correct: - Contract documents establish the formal requirements for the project. - They specify how often reports must be submitted and what information they must include. - This ensures all parties have the same expectations from the start. Why the other options are incorrect: - A. Monthly: While monthly reporting is common, it is not the minimum required in all cases. - B. As requested by the project manager: The project manager may request additional reports, but that is not the baseline requirement. - C. As requested by the owner: The owner may also request reports, but the contract documents determine the required minimum interval. In short, the reporting interval must follow what is written in the contract documents.
Right Answer: D
Quiz
Question 9/109/10
Which is NOT an industry-recognized methodology for quantifying critical delay?
Select the answer:Select the answer
1 correct answer
A.
Gantt Chart.
B.
Periodic Windows.
C.
Collapsed As-Built.
D.
Time Impact.
The correct answer is A. Gantt Chart. The question asks which option is not an industry-recognized methodology for quantifying critical delay. In construction delay analysis and forensic scheduling, there are several accepted methodologies used to measure the effect of delays on the project critical path and completion date. Why A is correct: A Gantt Chart is primarily a scheduling and planning tool. It is useful for displaying activities over time, but it is not itself a recognized delay analysis methodology. In other words, a Gantt chart shows the schedule; it does not provide a formal method for quantifying critical delay or performing a forensic delay analysis. Why the other options are recognized methods: B. Periodic Windows This refers to the Windows Analysis method, where the project schedule is divided into time periods or “windows” and the impact of delays is assessed within each period. It is a recognized forensic schedule analysis technique. C. Collapsed As-Built Also called the as-planned versus as-built approach in some contexts, this method starts with the as-built sequence and removes certain delays to estimate their effect on project completion. It is a recognized delay analysis methodology, though its acceptance may depend on the quality of records and assumptions used. D. Time Impact Time Impact Analysis is a widely recognized method used to assess the effect of a delay event by inserting a fragnet or delay activity into the schedule and recalculating completion dates. It is commonly used in project controls and delay claims. Summary: A Gantt chart is a visual scheduling format, not a formal critical delay quantification methodology. Therefore, A is the correct answer.
Right Answer: A
Quiz
Question 10/1010/10
What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?
Select the answer:Select the answer
1 correct answer
A.
ADM is limited to finish-to-start logic relationships, while PDM is not.
B.
PDM is a bar chart with network logic, while ADM is a pure logic network.
C.
ADM is manual CPM calculations, while PDM is computerized.
D.
ADM uses arrows, while PDM uses boxes.
The correct answer is A. The main difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM) is the type of logical relationships they support. - ADM uses only finish-to-start relationships. In ADM, activities are represented by arrows, and the sequence of work is shown by connecting those arrows with nodes. This method is more restrictive because the logic is limited to activities that must finish before the next one can start. - PDM is more flexible. In PDM, activities are shown as boxes, and the method can represent several types of relationships, including: - finish-to-start - start-to-start - finish-to-finish - start-to-finish Why the other options are incorrect: - B is incorrect because PDM is not a bar chart. A bar chart is a Gantt chart, which is different from both ADM and PDM. - C is incorrect because the difference is not whether calculations are manual or computerized. Both can be used in CPM scheduling, and either can be analyzed with software. - D is incomplete because although ADM does use arrows and PDM uses boxes, that is a format difference, not the primary difference. The key distinction is the kind of logic relationships each method can show. So the best answer is A: ADM is limited to finish-to-start logic relationships, while PDM is not.
AACE-PSP: AACE International Planning & Scheduling Professional (PSP) Practice test unlocks all online simulator questions
Thank you for choosing the free version of the AACE-PSP: AACE International Planning & Scheduling Professional (PSP) practice test! Further deepen your knowledge on AACE International Simulator; by unlocking the full version of our AACE-PSP: AACE International Planning & Scheduling Professional (PSP) Simulator you will be able to take tests with over 216 constantly updated questions and easily pass your exam. 98% of people pass the exam in the first attempt after preparing with our 216 questions.
What to expect from our AACE-PSP: AACE International Planning & Scheduling Professional (PSP) practice tests and how to prepare for any exam?
The AACE-PSP: AACE International Planning & Scheduling Professional (PSP) Simulator Practice Tests are part of the AACE International Database and are the best way to prepare for any AACE-PSP: AACE International Planning & Scheduling Professional (PSP) exam. The AACE-PSP: AACE International Planning & Scheduling Professional (PSP) practice tests consist of 216 questions and are written by experts to help you and prepare you to pass the exam on the first attempt. The AACE-PSP: AACE International Planning & Scheduling Professional (PSP) database includes questions from previous and other exams, which means you will be able to practice simulating past and future questions. Preparation with AACE-PSP: AACE International Planning & Scheduling Professional (PSP) Simulator will also give you an idea of the time it will take to complete each section of the AACE-PSP: AACE International Planning & Scheduling Professional (PSP) practice test . It is important to note that the AACE-PSP: AACE International Planning & Scheduling Professional (PSP) Simulator does not replace the classic AACE-PSP: AACE International Planning & Scheduling Professional (PSP) study guides; however, the Simulator provides valuable insights into what to expect and how much work needs to be done to prepare for the AACE-PSP: AACE International Planning & Scheduling Professional (PSP) exam.
AACE-PSP: AACE International Planning & Scheduling Professional (PSP) Practice test therefore represents an excellent tool to prepare for the actual exam together with our AACE International practice test . Our AACE-PSP: AACE International Planning & Scheduling Professional (PSP) Simulator will help you assess your level of preparation and understand your strengths and weaknesses. Below you can read all the quizzes you will find in our AACE-PSP: AACE International Planning & Scheduling Professional (PSP) Simulator and how our unique AACE-PSP: AACE International Planning & Scheduling Professional (PSP) Database made up of real questions:
Info quiz:
Quiz name:AACE-PSP: AACE International Planning & Scheduling Professional (PSP)
Total number of questions:216
Number of questions for the test:50
Pass score:80%
You can prepare for the AACE-PSP: AACE International Planning & Scheduling Professional (PSP) exams with our mobile app. It is very easy to use and even works offline in case of network failure, with all the functions you need to study and practice with our AACE-PSP: AACE International Planning & Scheduling Professional (PSP) Simulator.
Use our Mobile App, available for both Android and iOS devices, with our AACE-PSP: AACE International Planning & Scheduling Professional (PSP) Simulator . You can use it anywhere and always remember that our mobile app is free and available on all stores.
Our Mobile App contains all AACE-PSP: AACE International Planning & Scheduling Professional (PSP) practice tests which consist of 216 questions and also provide study material to pass the final AACE-PSP: AACE International Planning & Scheduling Professional (PSP) exam with guaranteed success.
Our AACE-PSP: AACE International Planning & Scheduling Professional (PSP) database contain hundreds of questions and AACE International Tests related to AACE-PSP: AACE International Planning & Scheduling Professional (PSP) Exam. This way you can practice anywhere you want, even offline without the internet.