The new flashcard feature is useful to memorize questions.
?Change your study mode
At any time, you can change the study mode, and alternate between the practice mode and the exam mode. In practice mode, you can configure for example the number of questions or tests, and other parameters to help you study.
Randomized | 10 Questions per Test | 20 Minutes | 70% to pass|
To re-configure your study mode again and change - for example - the number of tests, whether you have random questions and all other configuration parameters.
?Simulator Configuration
Auto-scroll: You can use the automatic scrolling of the questionnaire that occurs as soon as you answer one or all of the answers to a question correctly. Auto scrolling is activated if you answer a single answer, or as soon as you answer all the mandatory answers. Learning Mode: During learning mode you can get a real time result for your answer.
Free Test
Question: / 10
20:00Min. left
?Restart the current test
To restart the current test by clearing all your answers and the time used up to now. Warning: all answers will be lost.
Question: / 10
4.9(1375 Votes)
Quiz
Question 1/101/10
Once the project's WBS has been created what process may happen next?
Select the answer:Select the answer
1 correct answer
A.
Estimate activity resources
B.
Define activities
C.
Estimate activity durations
D.
Sequence activities
The define activities process is the process that may begin once the project's WBS has been completed and approved. It is possible, in some projects, to complete the WBS and the activity list at the same time. Answer option D is incorrect. Sequencing the activities cannot happen until the activity list has been created. Answer option A is incorrect. Estimating activity resources is dependent on the activity list, so this choice is not valid. Answer option C is incorrect. Estimate activity durations are dependent on the activity list, so this choice is not valid.
Right Answer: B
Quiz
Question 2/102/10
Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?
Select the answer:Select the answer
1 correct answer
A.
Precedence Diagramming Method
B.
Schedule network template
C.
Dependency determination
D.
Activity on the Node
The Precedence Diagramming Method uses both predecessors and successors as nodes in the project network diagram. The PDM approach is the most common network diagram approach used. Answer option C is incorrect. Dependency determination identifies the order of the project work. Answer option B is incorrect. The schedule network template is a tool that uses a previous project network diagram as a base for the current project network diagram. Answer option D is incorrect. Activity on the node laces activities on circles within a network diagram. It is an example of the precedence diagramming method.
Right Answer: A
Quiz
Question 3/103/10
You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders. What communication technique
do you normally use to distribute reports?
Select the answer:Select the answer
1 correct answer
A.
Push technique
B.
Many-to-many
C.
One-to-one
D.
Pull technique
Performance reports are distributed through the push technique. This means that the project manager distributes the reports regularly through a mechanism, such as email. Answer option C is incorrect. One-to-one technique describes a conversation between two people. Answer option B is incorrect. Many-to-many technique describes a conversation between many people. Answer option D is incorrect. A pull technique describes the recipients of the report "pulling" the information, such as from a Website.
Right Answer: A
Quiz
Question 4/104/10
Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement. Which approach could you use to shorten the duration of the project?
Select the answer:Select the answer
1 correct answer
A.
Perform resource leveling for the project.
B.
Crash the project schedule.
C.
Fast track the project.
D.
Remove things from the project scope.
Fast tracking is a technique for compressing project schedule. In fast tracking, phases are overlapped that would normally be done in sequence. It is shortening the project schedule without reducing the project scope. It does not add any additional labor but it can introduce project risks. Answer option D is incorrect. Removing things from the project scope can reduce the project duration, but it will not satisfy the requirements the stakeholders have identified. Answer option A is incorrect. Resource leveling can actually increase the project duration. Answer option B is incorrect. Crashing can reduce the project duration but it increases the labor expense, something the stakeholders won't approve.
Right Answer: C
Quiz
Question 5/105/10
The Define Activities process is the first process in the project time management knowledge are
a. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment. Which one of the following is not an output of the Define Activities process?
Select the answer:Select the answer
1 correct answer
A.
Activity list
B.
Milestone list
C.
Activity attributes
D.
Project document updates
Project document updates are not an output of the Define Activities process. Project document updates are the outputs for estimate activity resources. Project document updates include the following: Activity list Activity attributes Resource calendars Answer option A is incorrect. The activity list is an output of the define activities process. Answer option C is incorrect. The activity attributes is an output of the define activities process. Answer option B is incorrect. The milestone list is an output of the define activities process.
Right Answer: D
Quiz
Question 6/106/10
Examine the figure given below:
If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?
Select the answer:Select the answer
1 correct answer
A.
Three days
B.
One day
C.
Four days
D.
Zero days
Activity B is not on the critical path and it has a total of four days of float. If Activity B takes a total of eight days, it will consume three days of float. However, the total duration of the path ABEHJ may not exceed 26 days, as this is the total duration for the project. Although Activity H has a total of four days of float available, the consumption of three days of float on this path will reduce the total float for Activity H to just one day. If Activity H is delayed by more than one day, then the project will be late. Answer option D is incorrect. There is one day of float still available for Activity H. Answer options A and C are incorrect. These are not the valid answers, as there is just one day of float available for Activity H.
Right Answer: B
Quiz
Question 7/107/10
You are the project manager of the GHT Project. Ben, one of your project team members, does not understand the idea of a milestone. Which of the following best describes what a milestone is?
Select the answer:Select the answer
1 correct answer
A.
A significant point in the project
B.
A goal of reaching a significant delivery of project benefits by an identified date
C.
An imposed date for the project to reach a given point
D.
The completion of a project activity that is crucial to project completion
A milestone is simply a significant point or event in the project. It does not have to be assigned to a specific date, but is usually assigned to the completion of project phases. A milestone is the end of a stage that marks the completion of a work package or phase, typically mark d by a high level event such as completion, endorsement or signing of a deliverable, document or a high level review meeting. In addition to signaling the completion of a key deliverable, a milestone may also signify an important decision or the derivation of a critical piece of information, which outlines or affects the future of a project. In this sense, a milestone not only signifies distance traveled (key stages in a project) but also indicates direction of travel since key decisions made at milestones may alter the route through the project plan. To create a milestone, enter 0 (zero) in the Duration field. The task will automatically be classified as a milestone. Answer option C is incorrect. This is a project constraint. Answer option B is incorrect. A project goal is an objective for time, cost, scope, and other metrics. Answer option D is incorrect. All activities must be completed in order to complete the project work. Activities that are not completed are quality issues that prevent the project from completing the project scope.
Right Answer: A
Quiz
Question 8/108/10
You are the project manager of the GHY Project. Management wants you to create a process improvement plan for your project. Your project will be studied by management and will become a standard for all future organizational projects based on your project's performance, approach, and implementation of project processes. All of the following should be included in your project's process improvement plan except for which one?
Select the answer:Select the answer
1 correct answer
A.
Process boundaries
B.
Process configuration
C.
Targets for improved performance
D.
Identification of project risks
Identification of the project risks is not part of the process improvement plan. Identify risks is a risk management process, and risks are recorded in the risk register. Answer options A, B, and C are incorrect. Process boundaries, Process configuration and Targets for improved performance are parts of the process improvement plan.
Right Answer: D
Quiz
Question 9/109/10
George is the project manager of the NHQ Project and has a budget of $778,000. The project is scheduled to last for one year with an equal amount of work completed each quarter. The second quarter of the project has ended and George has spent $325,000 but has only finished forty percent of the project. Management needs a variance report for the project schedule. What value should George report in this instance?
Select the answer:Select the answer
1 correct answer
A.
.96
B.
-$77,800
C.
$-34,500
D.
-$13,800
Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that the schedule is ahead or behind what was planned for this period in time. The schedule variance is calculated based on the following formula: SV = Earned Value (EV) - Planned Value (PV) If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater than 0 shows that the project is ahead of the planned schedule. A value of 0 indicates that the project is right on target. The earned value in this instance is forty percent of the project budget, $778,000, and the planned value is $398,000 because George is to be fifty percent done at the end of the second quarter, as the work is spread evenly across all quarters. The schedule variance is -$77,800 for the project. Answer option A is incorrect. .96 represents the cost performance index. Answer option C is incorrect. -$34,500 represents the project's variance at completion if the project continues as is. Answer option D is incorrect. -$13,800 is the cost variance for the project.
Right Answer: B
Quiz
Question 10/1010/10
You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95. What does this term mean?
Select the answer:Select the answer
1 correct answer
A.
It means the largest schedule variance you can have is five percent.
B.
It is the earned value divided by the planned value for your project.
C.
It is the expectation of management to be 95 on schedule at 95 percent of the project.
D.
It means you will need to earn at least 95 cents per dollar invested in the project.
Conformance to schedule is a required adherence for the project's schedule. In this instance, the project manager must not allow the schedule to slip more than five percent. Answer option B is incorrect. This is the description of the schedule performance index. Answer option D is incorrect. This is the description of the cost performance index. Answer option C is incorrect. This is not a valid statement about the project performance.
PMI-SP: PMI Scheduling Professional Practice test unlocks all online simulator questions
Thank you for choosing the free version of the PMI-SP: PMI Scheduling Professional practice test! Further deepen your knowledge on PMI Simulator; by unlocking the full version of our PMI-SP: PMI Scheduling Professional Simulator you will be able to take tests with over 327 constantly updated questions and easily pass your exam. 98% of people pass the exam in the first attempt after preparing with our 327 questions.
What to expect from our PMI-SP: PMI Scheduling Professional practice tests and how to prepare for any exam?
The PMI-SP: PMI Scheduling Professional Simulator Practice Tests are part of the PMI Database and are the best way to prepare for any PMI-SP: PMI Scheduling Professional exam. The PMI-SP: PMI Scheduling Professional practice tests consist of 327 questions and are written by experts to help you and prepare you to pass the exam on the first attempt. The PMI-SP: PMI Scheduling Professional database includes questions from previous and other exams, which means you will be able to practice simulating past and future questions. Preparation with PMI-SP: PMI Scheduling Professional Simulator will also give you an idea of the time it will take to complete each section of the PMI-SP: PMI Scheduling Professional practice test . It is important to note that the PMI-SP: PMI Scheduling Professional Simulator does not replace the classic PMI-SP: PMI Scheduling Professional study guides; however, the Simulator provides valuable insights into what to expect and how much work needs to be done to prepare for the PMI-SP: PMI Scheduling Professional exam.
PMI-SP: PMI Scheduling Professional Practice test therefore represents an excellent tool to prepare for the actual exam together with our PMI practice test . Our PMI-SP: PMI Scheduling Professional Simulator will help you assess your level of preparation and understand your strengths and weaknesses. Below you can read all the quizzes you will find in our PMI-SP: PMI Scheduling Professional Simulator and how our unique PMI-SP: PMI Scheduling Professional Database made up of real questions:
Info quiz:
Quiz name:PMI-SP: PMI Scheduling Professional
Total number of questions:327
Number of questions for the test:50
Pass score:80%
You can prepare for the PMI-SP: PMI Scheduling Professional exams with our mobile app. It is very easy to use and even works offline in case of network failure, with all the functions you need to study and practice with our PMI-SP: PMI Scheduling Professional Simulator.
Use our Mobile App, available for both Android and iOS devices, with our PMI-SP: PMI Scheduling Professional Simulator . You can use it anywhere and always remember that our mobile app is free and available on all stores.
Our Mobile App contains all PMI-SP: PMI Scheduling Professional practice tests which consist of 327 questions and also provide study material to pass the final PMI-SP: PMI Scheduling Professional exam with guaranteed success.
Our PMI-SP: PMI Scheduling Professional database contain hundreds of questions and PMI Tests related to PMI-SP: PMI Scheduling Professional Exam. This way you can practice anywhere you want, even offline without the internet.