A PM is responsible for implementing a new customer relationship management system and has
learned that the sales organization is reluctant to utilize the new system. The organization's
reluctance could jeopardize the success of the project. Which of the following steps should be taken
to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).
Select the answer
2 correct answers
A.
Train users on the proper use of the system.
B.
Escalate the issue to the CCB
C.
Hold sessions to understand user challenges.
D.
Track system usage and report user activity.
E.
Log the issue in the project risk register.
F.
Create a memorandum of acceptable use.

Quiz

2/10
SIMULATION
During a gate review meeting, the deliverable was rejected by the customer.
INSTRUCTIONS
Review the dashboard.
• Part 1: Drag and drop each task, placing them in the correct order based on the project change
control process.
• Part 2: Select the proper document(s) to be updated.
If at any time you would like to bring back the initial state of the simulation, please click the Reset All
button.
Part 1:
Certification Exam PK0-005: CompTIA Project+ Certification CompTIA CompTIA-PK0-005 1-307956181

Part 2:
Certification Exam PK0-005: CompTIA Project+ Certification CompTIA CompTIA-PK0-005 2-2936829483
Select the answer
1 correct answer
Part 1:
Change Control Process:
Consult the RACI matrix.
Define new requirements and record changes.
Assess the schedule, risk, and cost.
Perform a demonstration.
Obtain a sign off.
Update and test the deliverable.
Make an announcement on the company portal.
The change control process is a sequence of steps that helps to manage and document any changes
or modifications to a project scope, schedule, cost, quality, or resources. The change control process
typically involves the following steps:
Consult the RACI matrix. A RACI matrix is a tool that defines and clarifies the roles and
responsibilities of each team member for each task or activity in a project. RACI stands for
responsible, accountable, consulted, and informed. Consulting the RACI matrix can help to identify
who needs to be involved or informed about the change request and how to communicate with
them.
Define new requirements and record changes. The new requirements and changes are the details of
what needs to be modified or added to the project deliverables or objectives based on the customer
feedback or request. Defining and recording the new requirements and changes can help to
communicate and justify the need and rationale for the change and its implications on the project
scope and quality.
Assess the schedule, risk, and cost. The schedule, risk, and cost are the aspects of the project that
may be affected by the change request. Assessing the schedule, risk, and cost can help to determine
the impact and feasibility of the change and identify any possible alternatives or corrective actions to
minimize or avoid its negative effects.
Perform a demonstration. A demonstration is a presentation or show of how the modified or
updated deliverable works or meets the customer expectations or requirements. Performing a
demonstration can help to validate and verify that the change request has been implemented
correctly and effectively and to obtain feedback or approval from the customer or stakeholders.
Obtain a sign off. A sign off is a formal acceptance and approval of the change request and its
deliverables from the customer or stakeholders. Obtaining a sign off can help to confirm that the
change request has been completed successfully and satisfactorily and to close the change control
process.
Update and test the deliverable. The deliverable is the product or service that is produced or
provided by the project. Updating and testing the deliverable can help to ensure that it meets the
quality standards and criteria and that it works as expected after implementing the change request.
Make an announcement on the company portal. The company portal is a platform or channel that
allows internal communication and collaboration among employees within an organization. Making
an announcement on the company portal can help to inform and update other team members or
departments about the change request and its outcomes and to share any lessons learned or best
practices from the change control process.
Part2:
Risk register: A risk register is a document that identifies, analyzes, and records the potential risks or
uncertainties that may affect a project. Updating the risk register can help to capture any new or
modified risks that may arise from the change request and to plan and implement appropriate risk
responses.
Schedule: A schedule is a document that shows the planned start and end dates, durations,
dependencies, and progress of each task or activity in a project. Updating the schedule can help to
reflect any changes or adjustments to the project timeline or milestones that may result from the
change request and to monitor and control the project performance and delivery.
Statement of work: A statement of work (SOW) is a document that defines the scope, deliverables,
schedule, and terms and conditions of a project or contract. Updating the SOW can help to document
any changes or additions to the project scope or deliverables that may be requested or agreed upon
by the customer or stakeholders and to ensure alignment and agreement on what needs to be done
and how it will be done.
Change log: A change log is a document that tracks and records any changes or modifications that are
made to the project scope, schedule, cost, quality, or resources during a project. Updating the
change log can help to document the change request, approval, implementation, and impact of each
change and ensure traceability and transparency.

Quiz

3/10
Following a successful release, a project manager sent a survey to all stakeholders to gain an
understanding of opportunity areas for the team. Which of the following can use the survey results
as an input?
Select the answer
1 correct answer
A.
Daily stand-up
B.
Project momentum
C.
Performance feedback
D.
Meeting minutes

Quiz

4/10
Which of the following is an activity that should be used in the closing phase of a project to support
the project triple constraint?
Select the answer
1 correct answer
A.
Evaluating the project
B.
Releasing the resources
C.
Closing the contracts
D.
Reconciling the budget

Quiz

5/10
During a quality analysis review, the causes of several issues have been highlighted. Which of the
following should the project manager use to identify the MOST important causes?
Select the answer
1 correct answer
A.
Ishikawa diagram
B.
Scatter diagram
C.
Pareto chart
D.
Decision tree

Quiz

6/10
Which of the following BEST describes how an organization should coordinate management of
multiple related projects?
Select the answer
1 correct answer
A.
Apply the SDLC process.
B.
Establish a program.
C.
Consult the CCB.
D.
Use different frameworks

Quiz

7/10
A project team gathers weekly to review its progress. Which of the following is the project manager
MOST likely to have prepared to ensure team members who are absent remain informed about
assignments?
Select the answer
1 correct answer
A.
Status report
B.
Project plan
C.
Change log
D.
Meeting minutes

Quiz

8/10
A project manager prefers to have immediate contact with team members because it allows for
faster response times and more interactive discussions. Which of the following communication
methods should the project manager use?
Select the answer
1 correct answer
A.
Synchronous
B.
Informal
C.
Asynchronous
D.
Formal

Quiz

9/10
As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the
following is the NEXT step in the process?
Select the answer
1 correct answer
A.
Update the work breakdown structure.
B.
Review the backlog.
C.
Seek baseline approval.
D.
Establish the resource pool.

Quiz

10/10
A project manager realizes that a project will not be completed on time due to resource constraints.
Which of the following actions should the project manager take NEXT?
Select the answer
1 correct answer
A.
Trigger the contingency plan and communicate with the stakeholders.
B.
Work with the functional managers to create a work-around.
C.
Submit a change request to the change control board.
D.
Transfer the risk by hiring a new vendor who was successful on a previous project.
E.
Set up an escalation meeting with the sponsor.
Looking for more questions?Buy now

PK0-005: CompTIA Project+ Certification Practice test unlocks all online simulator questions

Thank you for choosing the free version of the PK0-005: CompTIA Project+ Certification practice test! Further deepen your knowledge on CompTIA Simulator; by unlocking the full version of our PK0-005: CompTIA Project+ Certification Simulator you will be able to take tests with over 386 constantly updated questions and easily pass your exam. 98% of people pass the exam in the first attempt after preparing with our 386 questions.

BUY NOW

What to expect from our PK0-005: CompTIA Project+ Certification practice tests and how to prepare for any exam?

The PK0-005: CompTIA Project+ Certification Simulator Practice Tests are part of the CompTIA Database and are the best way to prepare for any PK0-005: CompTIA Project+ Certification exam. The PK0-005: CompTIA Project+ Certification practice tests consist of 386 questions and are written by experts to help you and prepare you to pass the exam on the first attempt. The PK0-005: CompTIA Project+ Certification database includes questions from previous and other exams, which means you will be able to practice simulating past and future questions. Preparation with PK0-005: CompTIA Project+ Certification Simulator will also give you an idea of the time it will take to complete each section of the PK0-005: CompTIA Project+ Certification practice test . It is important to note that the PK0-005: CompTIA Project+ Certification Simulator does not replace the classic PK0-005: CompTIA Project+ Certification study guides; however, the Simulator provides valuable insights into what to expect and how much work needs to be done to prepare for the PK0-005: CompTIA Project+ Certification exam.

BUY NOW

PK0-005: CompTIA Project+ Certification Practice test therefore represents an excellent tool to prepare for the actual exam together with our CompTIA practice test . Our PK0-005: CompTIA Project+ Certification Simulator will help you assess your level of preparation and understand your strengths and weaknesses. Below you can read all the quizzes you will find in our PK0-005: CompTIA Project+ Certification Simulator and how our unique PK0-005: CompTIA Project+ Certification Database made up of real questions:

Info quiz:

  • Quiz name:PK0-005: CompTIA Project+ Certification
  • Total number of questions:386
  • Number of questions for the test:50
  • Pass score:80%

You can prepare for the PK0-005: CompTIA Project+ Certification exams with our mobile app. It is very easy to use and even works offline in case of network failure, with all the functions you need to study and practice with our PK0-005: CompTIA Project+ Certification Simulator.

Use our Mobile App, available for both Android and iOS devices, with our PK0-005: CompTIA Project+ Certification Simulator . You can use it anywhere and always remember that our mobile app is free and available on all stores.

Our Mobile App contains all PK0-005: CompTIA Project+ Certification practice tests which consist of 386 questions and also provide study material to pass the final PK0-005: CompTIA Project+ Certification exam with guaranteed success. Our PK0-005: CompTIA Project+ Certification database contain hundreds of questions and CompTIA Tests related to PK0-005: CompTIA Project+ Certification Exam. This way you can practice anywhere you want, even offline without the internet.

BUY NOW