The new flashcard feature is useful to memorize questions.
?Change your study mode
At any time, you can change the study mode, and alternate between the practice mode and the exam mode. In practice mode, you can configure for example the number of questions or tests, and other parameters to help you study.
Randomized | 10 Questions per Test | 20 Minutes | 70% to pass|
To re-configure your study mode again and change - for example - the number of tests, whether you have random questions and all other configuration parameters.
?Simulator Configuration
Auto-scroll: You can use the automatic scrolling of the questionnaire that occurs as soon as you answer one or all of the answers to a question correctly. Auto scrolling is activated if you answer a single answer, or as soon as you answer all the mandatory answers. Learning Mode: During learning mode you can get a real time result for your answer.
Free Test
Question: / 10
20:00Min. left
?Restart the current test
To restart the current test by clearing all your answers and the time used up to now. Warning: all answers will be lost.
Question: / 10
5.0(1578 Votes)
Quiz
Question 1/101/10
Early in a project stakeholder analysis is performed: however, an organizational restructure redefines key roles What should the project team do?
Select the answer:Select the answer
1 correct answer
A.
Note the changes to the restructure and roles that affect team activities
B.
Use direct engagement and two-way conversation to update the stakeholder analysis for any new stakeholder requirements.
C.
Email a copy of the project vision to those redefined for key roles and ask if they need to be involved in the project
D.
Obtain a copy of the redefined key roles to update the stakeholder analysis
The correct answer is B. Use direct engagement and two-way conversation to update the stakeholder analysis for any new stakeholder requirements. Stakeholder analysis is not a one-time activity. It should be reviewed and updated whenever there is a significant change in the organization or project environment. An organizational restructure can change: - who the stakeholders are - their authority and influence - their interests and expectations - their level of impact on the project - new requirements or concerns they may have Why B is correct: - It emphasizes direct engagement with the affected stakeholders. - Two-way conversation helps the team understand new needs, expectations, and concerns. - Stakeholder analysis should be updated based on current, accurate information gathered from the stakeholders themselves, not just from documents or assumptions. - This aligns with good stakeholder management practice: identify changes, engage the right people, and revise the analysis accordingly. Why the other options are not best: A. Note the changes to the restructure and roles that affect team activities - This is too passive. - Simply noting the changes does not ensure the stakeholder analysis is updated or that new requirements are discovered. C. Email a copy of the project vision to those redefined for key roles and ask if they need to be involved in the project - Email alone is not enough for proper stakeholder analysis. - It is a one-way communication and may miss important concerns or changes in expectations. - The question specifically calls for stakeholder analysis updates, which require active engagement. D. Obtain a copy of the redefined key roles to update the stakeholder analysis - This may help identify changes, but it is not sufficient by itself. - A role description does not reveal stakeholder attitudes, concerns, influence, or requirements. - Stakeholder analysis requires more than an organizational chart or list of roles. Key takeaway: When organizational changes occur, the project team should re-engage stakeholders directly and update the stakeholder analysis based on two-way communication. This makes B the best answer.
Right Answer: B
Quiz
Question 2/102/10
An experienced product owner presents the epics and corresponding stones during a release planning session with the established team. The executive sponsor asks the team when the features will be delivered. What should the agile team do?
Select the answer:Select the answer
1 correct answer
A.
Evaluate how much can be delivered based on the Scrum Master's estimation
B.
Identify a set of user stones based on the team's velocity
C.
Initiate an estimation session
D.
Consult historical data for project completion
The correct answer is C. Initiate an estimation session. In an agile release planning session, the executive sponsor wants to know when features will be delivered. At this point, the team should not guess or rely only on historical data or a single person’s estimate. Instead, the team should collaboratively estimate the work so that the forecast is based on the team’s shared understanding of the epics and stories. Why C is correct: - Estimation is the right next step when the team needs a delivery forecast. - The team should use a collaborative estimation approach, such as planning poker or another team-based estimation method. - This helps the team understand scope, complexity, and uncertainty before making any commitment about delivery dates. Why the other options are not correct: A. Evaluate how much can be delivered based on the Scrum Master's estimation - The Scrum Master does not estimate the work for the team. - In agile, estimation should come from the team members who will do the work. B. Identify a set of user stones based on the team's velocity - The term "user stones" is not standard agile terminology; it likely refers to user stories. - Velocity can help with forecasting later, but the team must first estimate the backlog items. - Without estimation of the stories, velocity alone is not enough to answer the sponsor’s question accurately. D. Consult historical data for project completion - Historical data can support forecasting, but it is not sufficient by itself for this specific planning session. - The team needs current estimation of the presented epics and stories to make a meaningful release forecast. Summary: When asked when features will be delivered, the agile team should first estimate the work collaboratively. That is why initiating an estimation session is the best answer.
Right Answer: C
Quiz
Question 3/103/10
While struggling to take ownership of delivery an agile team fails to keep up with its sprint commitments What should the agile coach do?
Select the answer:Select the answer
1 correct answer
A.
Work with the sponsor to develop team expectations
B.
Provide the customer with a list of deliverables and obtain agreement
C.
Encourage the team to more frequently interact with all stakeholders
D.
Work on finishing upfront product design rather than comprehensive documentation
The correct answer is C. Encourage the team to more frequently interact with all stakeholders. When an agile team is struggling to take ownership of delivery and is not meeting sprint commitments, the agile coach should focus on improving collaboration, communication, and stakeholder engagement. Agile teams work best when they have frequent feedback from stakeholders, which helps them clarify priorities, identify misunderstandings early, and adapt quickly. Why C is correct: - Agile emphasizes regular interaction with stakeholders over relying on detailed upfront plans. - If the team is missing sprint commitments, one likely issue is poor alignment with business needs, unclear priorities, or lack of timely feedback. - Encouraging more frequent stakeholder interaction helps the team: - better understand expectations, - improve commitment planning, - adjust work based on feedback, - take greater ownership of delivery. Why the other options are incorrect: A. Work with the sponsor to develop team expectations - This is too management-focused and does not directly help the team improve its agile delivery behavior. - Agile teams should be empowered to own their commitments rather than have expectations imposed primarily through the sponsor. B. Provide the customer with a list of deliverables and obtain agreement - This sounds more like a traditional project-management approach than an agile one. - Agile teams do not typically rely on fixed deliverable lists upfront; instead, they use ongoing collaboration and adaptation. D. Work on finishing upfront product design rather than comprehensive documentation - Agile values just enough design and documentation, but the issue described is not about documentation. - Emphasizing upfront design can reduce agility and does not address the team’s lack of delivery ownership or sprint commitment issues. Summary: The coach should help the team improve communication and collaboration with stakeholders so they can better understand priorities, gain feedback faster, and take stronger ownership of delivery. That is why C is the best answer.
Right Answer: C
Quiz
Question 4/104/10
A development team and product owner disagree on a user story in the product backlog What should the agile practitioner do?
Select the answer:Select the answer
1 correct answer
A.
Have the development team follow the product owner's direction
B.
Openly challenge the product owner in an effort to poke holes in their approach
C.
Facilitate a conversation about the user story between the development team and the product owner
D.
Serve as a nonpartisan evaluator of each option, and provide direction to the development team and product owner
The correct answer is C. Facilitate a conversation about the user story between the development team and the product owner. In an agile environment, the product owner and the development team may have different perspectives about a user story. The product owner is responsible for maximizing product value and setting priorities, while the development team is responsible for understanding the work needed to deliver the story effectively. When there is disagreement, the agile practitioner should not take sides or impose a decision. Instead, the best action is to help both parties communicate openly and collaborate toward a shared understanding. Why C is correct: - It encourages collaboration and transparency. - It allows both the product owner and the development team to explain their reasoning. - It helps the team reach a solution that balances business value, feasibility, and delivery concerns. - It supports agile principles of self-management and continuous conversation. Why the other options are incorrect: A. Have the development team follow the product owner's direction - This ignores the development team's expertise and input. - Agile teams are collaborative, not command-and-control. B. Openly challenge the product owner in an effort to poke holes in their approach - This creates conflict rather than collaboration. - The goal is to facilitate constructive discussion, not adversarial debate. D. Serve as a nonpartisan evaluator of each option, and provide direction to the development team and product owner - The agile practitioner should not act as the decision-maker for the team. - Agile practitioners help enable discussion and team alignment, but they typically do not direct the work or arbitrate product decisions. Summary: When the development team and product owner disagree, the agile practitioner should facilitate communication so they can resolve the issue together. This preserves collaboration, respects each role, and supports agile ways of working.
Right Answer: C
Quiz
Question 5/105/10
Toward the end of a project the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected What should the product owner do?
Select the answer:Select the answer
1 correct answer
A.
Terminate the project to cut losses
B.
Review possible options and make an informed decision to cut losses based on delivered business value
C.
Bring in experts to increase the probability of success
D.
Continue the project release the product without the failing feature and fix the feature in a subsequent release
The correct answer is D. Continue the project, release the product without the failing feature, and fix the feature in a subsequent release. Why this is correct In an agile or product-focused environment, the product owner’s main responsibility is to maximize value delivery. If a critical feature is not functioning as expected near the end of a project, the best response is often to assess whether the product can still provide usable value without that feature. If it can, the product can be released in a reduced or partial form, and the missing or broken feature can be addressed later in a follow-up release. This approach aligns with these principles: - Deliver value as early as possible - Avoid unnecessary delay - Adapt to changing conditions - Make decisions based on business value, not just completion of scope Why the other options are not the best answer A. Terminate the project to cut losses This is too extreme and premature. A project with one failing feature is not automatically a failed project. If the remaining product still has value, ending the project would waste useful work and potentially miss an opportunity to deliver something worthwhile. B. Review possible options and make an informed decision to cut losses based on delivered business value This sounds reasonable in general, but it implies stopping the project if value is insufficient. The question asks what the product owner should do toward the end of the project when one critical feature is failing. The better agile response is to consider releasing what works and postponing the problematic feature if that still provides value. C. Bring in experts to increase the probability of success This may help, but it is not necessarily the best action at the end of a project. At that stage, the key question is whether the product can still deliver value in its current state. Bringing in experts may delay release and does not directly address the product owner’s decision about value. Key idea The product owner should focus on maximizing business value and making pragmatic release decisions. If the product can still be useful without the failing feature, releasing it now and fixing the feature later is often the best choice. If you'd like, I can also explain why this is the best answer from a Scrum perspective specifically.
Right Answer: D
Quiz
Question 6/106/10
During planning for the next iteration an agile team identifies most of the story points that are expected to be delivered How should an agile practitioner work with the team to help identify the iteration's remaining scope?
Select the answer:Select the answer
1 correct answer
A.
Convince the team to stop planning and keep the size small
B.
Identify the technically minimal and achievable tasks
C.
Refer to the remaining prioritized backlog items
D.
Select some of the smallest items from the backlog
The correct answer is C. Refer to the remaining prioritized backlog items. In agile planning, the team first selects the highest-priority work for the iteration based on its expected capacity and velocity. If most of the planned story points have already been identified and there is still room left in the iteration, the next step is to look at the remaining prioritized backlog items and continue selecting the next most valuable work. Why C is correct: - The product backlog is ordered by priority. - The team should fill any remaining capacity with the next most important items. - This ensures the iteration continues to deliver maximum value rather than just choosing work that is small or convenient. Why the other options are not correct: - A. Convince the team to stop planning and keep the size small - Agile does not mean avoiding planning. The team should plan enough work to make the iteration goal meaningful while staying within capacity. - B. Identify the technically minimal and achievable tasks - This focuses on technical simplicity rather than business priority or value, which is not the main principle for selecting iteration scope. - D. Select some of the smallest items from the backlog - Small items may be easy to fit in, but size alone should not determine selection. Priority and value are more important. Key takeaway: When an iteration still has room after selecting the initial scope, the team should pull the next highest-priority items from the backlog, not just the smallest or easiest ones.
Right Answer: C
Quiz
Question 7/107/10
The risk profile of a project has increased beyond the upper threshold of tolerance. The product owner and project leader meet to discuss an approach for dealing with this. What should the team do next?
Select the answer:Select the answer
1 correct answer
A.
Add risk mitigation tasks to the backlog, then prioritize in current and upcoming sprints
B.
Add risk mitigation time to each requirement
C.
Apply the 80/20 rule, reserving 20 percent of each sprint’s capacity for risk mitigation
D.
Hold all risks until they become issues, then add issue resolution tasks to the product backlog
The correct answer is A. Add risk mitigation tasks to the backlog, then prioritize in current and upcoming sprints. When a project’s risk profile rises above the agreed tolerance threshold, the team should respond proactively. In an Agile environment, that means treating risk mitigation work as planned work and making it visible in the backlog. The product owner and project leader should discuss the risk, decide on appropriate mitigation actions, and then have those actions added to the backlog so they can be prioritized against other work. Why A is correct: - It makes risk response explicit and visible. - It allows the product owner to prioritize mitigation based on business value and urgency. - It fits Agile planning, where work is managed through the backlog and reprioritized as conditions change. - It can be addressed in the current sprint if the risk is urgent, or in future sprints if appropriate. Why the other options are not correct: B. Add risk mitigation time to each requirement - This is too broad and not very practical. - Risk mitigation should be handled based on actual risks, not automatically embedded into every requirement. - It does not provide a clear prioritization mechanism. C. Apply the 80/20 rule, reserving 20 percent of each sprint’s capacity for risk mitigation - This is not a standard Agile or risk management practice. - Reserving a fixed percentage of capacity regardless of actual risk is arbitrary. - Risk response should be based on current risk exposure, not a preset capacity rule. D. Hold all risks until they become issues, then add issue resolution tasks to the product backlog - This is reactive, not proactive. - Good risk management aims to reduce the chance or impact of risks before they become actual problems. - Waiting until risks become issues can lead to delays, higher costs, and more disruption. Summary: Because the risk level has exceeded tolerance, the team should actively respond by adding risk mitigation tasks to the backlog and prioritizing them appropriately. That is why A is the best answer.
Right Answer: A
Quiz
Question 8/108/10
An agile team is planning the next iteration for a product release that has accumulated technical debt What should the team do?
Select the answer:Select the answer
1 correct answer
A.
Add code cleanup activities to the product backlog and request prioritization by the product owner
B.
Add code cleanup activities to the next iteration and request clarification from the product owner
C.
Add code cleanup activities to the next iteration and ask the product owner to end the current iteration
D.
Add code cleanup activities to the next release backlog and request documentation from the product owner
The correct answer is A. Add code cleanup activities to the product backlog and request prioritization by the product owner. Why this is correct In agile, technical debt should be made visible and managed as part of the product backlog. It is not something the team should simply hide inside the next iteration without discussion. By adding code cleanup work to the backlog, the team ensures that the work is transparent, estimable, and can be prioritized alongside other product needs. The product owner is responsible for ordering the backlog based on business value, risk, and urgency. Since technical debt can affect future delivery speed, quality, and maintainability, the team should bring it to the product owner for prioritization. Why the other options are incorrect B. Add code cleanup activities to the next iteration and request clarification from the product owner This is less appropriate because the team should not unilaterally insert work into the next iteration without backlog prioritization. Also, technical debt usually does not require “clarification” from the product owner; it requires prioritization. C. Add code cleanup activities to the next iteration and ask the product owner to end the current iteration An iteration should not be ended early just to deal with technical debt. Agile teams work within the timebox of the iteration. Ending the iteration early would be disruptive and is not the proper approach. D. Add code cleanup activities to the next release backlog and request documentation from the product owner Technical debt should be handled in the product backlog, not a vague “release backlog.” Also, asking the product owner for documentation does not address the issue of prioritizing and planning the technical debt work. Key takeaway Technical debt should be visible, added to the product backlog, and prioritized by the product owner like any other work item.
Right Answer: A
Quiz
Question 9/109/10
How can an agile team working on a new product ensure alignment with external stakeholders?
Select the answer:Select the answer
1 correct answer
A.
Ask the product owner to provide a detailed product specification document
B.
Conduct story-mapping exercises to clarify deliverables and release priorities
C.
Hold a kick-off meeting to assign roles and responsibilities.
D.
Work with the scrum master and stakeholders to ensure agile principles are followed
The correct answer is B. Conduct story-mapping exercises to clarify deliverables and release priorities. An agile team working on a new product needs a way to align everyone around what will be built, in what order, and why. Story mapping is especially useful for this because it helps the team and external stakeholders create a shared visual understanding of the product. Why B is correct: - Story mapping organizes user activities, features, and stories in a way that shows the full product flow. - It helps stakeholders see the big picture and understand how the product will be delivered incrementally. - It supports prioritization by identifying which features are essential for early releases and which can come later. - It encourages collaboration and frequent feedback, which is central to agile ways of working. Why the other options are less suitable: - A. Ask the product owner to provide a detailed product specification document - Agile values collaboration and adaptability over heavy up-front documentation. - A detailed specification can become outdated quickly and may reduce stakeholder involvement. - C. Hold a kick-off meeting to assign roles and responsibilities - This may help at the start of a project, but it does not ensure ongoing alignment about deliverables and priorities. - D. Work with the scrum master and stakeholders to ensure agile principles are followed - While agile principles are important, this is too general. - It does not provide a concrete technique for aligning on what the product should contain and how releases should be prioritized. In summary, story mapping is the best option because it directly supports shared understanding, prioritization, and alignment with external stakeholders on a new product.
Right Answer: B
Quiz
Question 10/1010/10
An agile project manager is planning the initial scope, schedule and cost range estimates on a new project. The team will be using Kanban to control work. What metrics should the team use to measure performance?
Select the answer:Select the answer
1 correct answer
A.
Lead time, throughput and due date performance
B.
Work in progress limits Kanban board, and time boxes
C.
Work item types, sprint cadences, and defect classes
D.
Burndown charts, scatter diagrams, and throughput
The correct answer is A. Lead time, throughput and due date performance. Here is why: In Kanban, the team focuses on measuring flow and predictability rather than using fixed iterations or sprint-based measures. Since the project manager is estimating initial scope, schedule, and cost ranges, the most useful metrics are those that show how work moves through the system and how reliably the team delivers. Let’s look at the key metrics in Option A: - Lead time: The total time from when a work item is requested until it is completed. This helps the team understand how long work typically takes end to end. - Throughput: The number of work items completed in a given period. This shows the team’s delivery rate and supports forecasting. - Due date performance: How often the team completes work by the expected due date. This helps measure predictability and schedule reliability. These three metrics are especially useful in Kanban because they support forecasting based on actual flow data. They can help the project manager create range estimates for schedule and cost. Why the other options are not correct: B. Work in progress limits, Kanban board, and time boxes - These are practices or tools, not performance metrics. - WIP limits and time boxes help manage flow, but they do not directly measure performance. C. Work item types, sprint cadences, and defect classes - These are more related to Scrum or quality classification concepts. - Sprint cadence is not a Kanban performance metric. D. Burndown charts, scatter diagrams, and throughput - Throughput is relevant, but burndown charts are more associated with Scrum. - Scatter diagrams can be useful for analyzing relationships, but they are not one of the primary Kanban performance metrics in this context. In summary, Kanban performance is best measured by flow-based metrics such as lead time, throughput, and due date performance, which is why A is correct.
PMI-ACP: PMI Agile Certified Practitioner Practice test unlocks all online simulator questions
Thank you for choosing the free version of the PMI-ACP: PMI Agile Certified Practitioner practice test! Further deepen your knowledge on PMI Simulator; by unlocking the full version of our PMI-ACP: PMI Agile Certified Practitioner Simulator you will be able to take tests with over 480 constantly updated questions and easily pass your exam. 98% of people pass the exam in the first attempt after preparing with our 480 questions.
What to expect from our PMI-ACP: PMI Agile Certified Practitioner practice tests and how to prepare for any exam?
The PMI-ACP: PMI Agile Certified Practitioner Simulator Practice Tests are part of the PMI Database and are the best way to prepare for any PMI-ACP: PMI Agile Certified Practitioner exam. The PMI-ACP: PMI Agile Certified Practitioner practice tests consist of 480 questions and are written by experts to help you and prepare you to pass the exam on the first attempt. The PMI-ACP: PMI Agile Certified Practitioner database includes questions from previous and other exams, which means you will be able to practice simulating past and future questions. Preparation with PMI-ACP: PMI Agile Certified Practitioner Simulator will also give you an idea of the time it will take to complete each section of the PMI-ACP: PMI Agile Certified Practitioner practice test . It is important to note that the PMI-ACP: PMI Agile Certified Practitioner Simulator does not replace the classic PMI-ACP: PMI Agile Certified Practitioner study guides; however, the Simulator provides valuable insights into what to expect and how much work needs to be done to prepare for the PMI-ACP: PMI Agile Certified Practitioner exam.
PMI-ACP: PMI Agile Certified Practitioner Practice test therefore represents an excellent tool to prepare for the actual exam together with our PMI practice test . Our PMI-ACP: PMI Agile Certified Practitioner Simulator will help you assess your level of preparation and understand your strengths and weaknesses. Below you can read all the quizzes you will find in our PMI-ACP: PMI Agile Certified Practitioner Simulator and how our unique PMI-ACP: PMI Agile Certified Practitioner Database made up of real questions:
You can prepare for the PMI-ACP: PMI Agile Certified Practitioner exams with our mobile app. It is very easy to use and even works offline in case of network failure, with all the functions you need to study and practice with our PMI-ACP: PMI Agile Certified Practitioner Simulator.
Use our Mobile App, available for both Android and iOS devices, with our PMI-ACP: PMI Agile Certified Practitioner Simulator . You can use it anywhere and always remember that our mobile app is free and available on all stores.
Our Mobile App contains all PMI-ACP: PMI Agile Certified Practitioner practice tests which consist of 480 questions and also provide study material to pass the final PMI-ACP: PMI Agile Certified Practitioner exam with guaranteed success.
Our PMI-ACP: PMI Agile Certified Practitioner database contain hundreds of questions and PMI Tests related to PMI-ACP: PMI Agile Certified Practitioner Exam. This way you can practice anywhere you want, even offline without the internet.